Restoration Update October 30, 2013


Latest restoration news:

Work completed:



  • The sub-floor has been installed in the living room.  
  • Forced hot air heat has been returned to the second floor, the basement, the kitchen and the pantry.  (There's no heat in the living room, so it's a bit chilly!) 
  • Channels have been opened in the walls of the living room in anticipation of installation of the fire suppression system
  •  John Larkin's desk has been moved to the Foster House, so that restoration of the foyer floor can be started.  (Of course, this is not original to Graycliff....)


Work currently in progress includes:


  •  Removal of mastic remaining from the linoleum that had been installed over the original wood floors by the Piarist Fathers, in the dining room and the entry foyer
  • In the basement, an electricition is working on wiring and routing for the fire suppression system
Will post some photos tomorrow!